xilinx leadtimes - Antti - 2010-07-04 05:18:00

Avnet is sole disti for Xilinx, now lets see what
Avnet says:

searching for Spartan-6
all items are no stock, with notice factory leadtime 16 weeks
but some items have extra note, "stock in asia"
good this means there is stock?
but what does the "stock in asia" link do?

it opens a popup window saying: no stock,
factory leadtime 143 weeks!

143 weeks leadtime on spartan-6?

should we all smile or cry?

Antti



Re: xilinx leadtimes - John Adair - 2010-07-04 06:51:00

It's even better when that 143 week lead time
comes through as a
formal quote. I have a number of Jan2013 delivery quotations. I'm sure
it's not as bad as that but the people on the ground at Avnet think
but they do go by their system quoted leadtimes.

Meanwhile I will announce a new Spartan-6 board later this week. We
have a limited supply of silicon sold to me by Nuho when they were
still franchaise but after that I guess it's maybe a wait until 2013.

John Adair
Enterpoint Ltd.


On 4 July, 10:18, Antti <antti.luk...@googlemail.com> wrote:
> Avnet is sole disti for Xilinx, now lets see what Avnet says:
>
> searching for Spartan-6
> all items are no stock, with notice factory leadtime 16 weeks
> but some items have extra note, "stock in asia"
> good this means there is stock?
> but what does the "stock in asia" link do?
>
> it opens a popup window saying: no stock,
> factory leadtime 143 weeks!
>
> 143 weeks leadtime on spartan-6?
>
> should we all smile or cry?
>
> Antti


Re: xilinx leadtimes - Frank Buss - 2010-07-04 07:17:00

Antti wrote:

> Avnet is sole disti for Xilinx, now lets see what Avnet says:
> 
> searching for Spartan-6
> all items are no stock, with notice factory leadtime 16 weeks
> but some items have extra note, "stock in asia"
> good this means there is stock?
> but what does the "stock in asia" link do?
> 
> it opens a popup window saying: no stock,
> factory leadtime 143 weeks!
> 
> 143 weeks leadtime on spartan-6?
> 
> should we all smile or cry?

Switch to Altera. I've never heard of delivery problems for the Cyclone 2,
which a customer is still using for a product which I helped to program.
Even for the latest Cyclone 4 there are already some chips available in the
Altera online shop. For the Cyclone 3 device there are hundreds of each
type in stock. Digikey, Farnell and other distributors have it in stock,
too.

16 weeks should be enough time for changing a design from one vendor to the
other, if you didn't use special features which are not available in the
other FPGA. And in the end you'll have a more FPGA independant design, if
you need to change it again :-)

-- 
Frank Buss, f...@frank-buss.de
http://www.frank-buss.de, http://www.it4-systems.de

Re: xilinx leadtimes - Uwe Bonnes - 2010-07-04 07:29:00

Antti <a...@googlemail.com> wrote:
> Avnet is sole disti for Xilinx, now lets see what Avnet says:

> searching for Spartan-6
> all items are no stock, with notice factory leadtime 16 weeks
> but some items have extra note, "stock in asia"
> good this means there is stock?
> but what does the "stock in asia" link do?

> it opens a popup window saying: no stock,
> factory leadtime 143 weeks!

> 143 weeks leadtime on spartan-6?

Digikey now also  has 251 XC6SLX items. All not on stock, but must parts
scheduled around mid of august .
-- 
Uwe Bonnes                b...@elektron.ikp.physik.tu-darmstadt.de

Institut fuer Kernphysik  Schlossgartenstrasse 9  64289 Darmstadt
--------- Tel. 06151 162516 -------- Fax. 06151 164321 ----------
______________________________
Join the blogging team on FPGARelated.com and earn rewards! Details Here.

Re: xilinx leadtimes - John Adair - 2010-07-04 09:33:00

On some these they will come back and say order
book isn't open.
That's what happened to me. I placed a pile of orders this way when
this list appeared mid-week as a emergency way to get silicon and an
alternative to Avnet. However I suspect, given what I have seen, that
they will meet these dates but you never know/

John Adair
Enterpoint Ltd.

On 4 July, 12:29, Uwe Bonnes <b...@elektron.ikp.physik.tu-
darmstadt.de> wrote:
> Antti <antti.luk...@googlemail.com> wrote:
> > Avnet is sole disti for Xilinx, now lets see what Avnet says:
> > searching for Spartan-6
> > all items are no stock, with notice factory leadtime 16 weeks
> > but some items have extra note, "stock in asia"
> > good this means there is stock?
> > but what does the "stock in asia" link do?
> > it opens a popup window saying: no stock,
> > factory leadtime 143 weeks!
> > 143 weeks leadtime on spartan-6?
>
> Digikey now also =A0has 251 XC6SLX items. All not on stock, but must part=
s
> scheduled around mid of august .
> --
> Uwe Bonnes =A0 =A0 =A0 =A0 =A0 =A0 =A0 =A0b...@elektron.ikp.physik.tu-dar=
mstadt.de
>
> Institut fuer Kernphysik =A0Schlossgartenstrasse 9 =A064289 Darmstadt
> --------- Tel. 06151 162516 -------- Fax. 06151 164321 ----------


Re: xilinx leadtimes - rickman - 2010-07-04 20:37:00

On Jul 4, 5:18=A0am, Antti
<antti.luk...@googlemail.com> wrote:
> Avnet is sole disti for Xilinx, now lets see what Avnet says:
>
> searching for Spartan-6
> all items are no stock, with notice factory leadtime 16 weeks
> but some items have extra note, "stock in asia"
> good this means there is stock?
> but what does the "stock in asia" link do?
>
> it opens a popup window saying: no stock,
> factory leadtime 143 weeks!
>
> 143 weeks leadtime on spartan-6?
>
> should we all smile or cry?
>
> Antti


What's the lead time for Spartan 5 parts?  Or how about Altera or
Lattice parts?  Why look for trouble?

Rick
______________________________
Join the blogging team on FPGARelated.com and earn rewards! Details Here.

Re: xilinx leadtimes - glen herrmannsfeldt - 2010-07-05 03:54:00

rickman <g...@gmail.com> wrote:
(snip)
 
> What's the lead time for Spartan 5 parts?  Or how about Altera or
> Lattice parts?  Why look for trouble?

I believe the lead time for Spartan 5, as with Spartan 4, is
much longer, likely approaching infinity.

Spartan 6 does have some interesting new features previously
only in Virtex devices.

-- glen

Re: xilinx leadtimes - maxascent - 2010-07-05 06:49:00

I think the problem is that if people want the
very latest and greatesttech they need to put up with long lead times and bugs in the developmentsoftware. Personally I would wait until these things are resolved and justuse a slightly older techology. 

Jon 	   
					
---------------------------------------		
Posted through http://www.FPGARelated.com

Re: xilinx leadtimes - Michael S - 2010-07-05 06:57:00

On Jul 5, 2:37=A0am, rickman
<gnu...@gmail.com> wrote:
>
> What's the lead time for Spartan 5 parts? =A0

Don't you mean Spartan 3E?

> Or how about Altera or
> Lattice parts? =A0Why look for trouble?
>
> Rick

Don't know about Lattice.

As to Altera, Spartan 6 has many features not available in Cyclone2/3.
Lead time for Cyclone IV is probably not much shorter than for Spartan
6. Also, Spartan 6 is both build on more modern silicon process and
has more advanced LUT architecture than even Cyclone IV, so, in
theory, it should be faster.
Of course, there is Arria II GX that easily matches (and beats)
Spartan 6 feature4feature and MHz4Mhz. It is even sort of available,
at least some parts. However, Arria II GX is more like mid-cost device
rather than low-cost.

______________________________
Join the blogging team on FPGARelated.com and earn rewards! Details Here.

Re: xilinx leadtimes - Michael S - 2010-07-05 07:03:00

On Jul 5, 12:49=A0pm, "maxascent"
<maxascent@n_o_s_p_a_m.n_o_s_p_a_m.yahoo.co.uk> wrote:
> I think the problem is that if people want the very latest and greatest
> tech they need to put up with long lead times and bugs in the development
> software. Personally I would wait until these things are resolved and jus=
t
> use a slightly older techology.
>
> Jon =A0 =A0 =A0 =A0
>
> --------------------------------------- =A0 =A0 =A0 =A0
> Posted throughhttp://www.FPGARelated.com

Around 10/2009 we were forced by our customer to work with Stratix IV
GX. What a nightmare! Until Quartus9.1 SP1 pretty much nothing worked
as expected. Were we starting the same project around 03/2010 it would
be walk in the park.
______________________________